Processing of car parks in newly-constructed buildings with predominantly residential use

Who can apply? Individuals and legal entities (through previously disclosed legal representative).

Documentation required

There are two phases in the processing procedure.

PHASE 1. Documentation required in order to obtain the urban planning license

  • Application for planning permission of works.
  • Basic building plan with the contents of annex 2, Law 7/2013, or with this content in technical documentation attached to the basic plan. Subsequently, with the execution plan, the activities plan must be provided, or the complete activities plan must be provided from the beginning.
  • Duly completed statement of compliance by the technician or the competent technician, in the event that the endorsed technical documentation is not submitted.

PHASE 2. Documentation required for the beginning and duration of the activity

  • Duly completed. Statement of compliance for the start and exercise of permanent activity.
  • Duly completed technical certificate of activity, with plans of the final state of the facilities.
  • Duly completed statement of compliance by the technician or the competent technician, in the event that the endorsed technical documentation is not submitted.
  • Technical certificate provided by the project manager

The entire documentation must also be submitted in electronic form as a pdf.

Where do I apply? At the Municipal Offices General Registry or via the Electronic Registry of the Town Hall’s electronic headquarters www.santaeulariadesriu.com (provided that you have an electronic signature, according to article 10, Law 39/2015).

Price and payment method

  • Self-assessment generated by the General Registry in view of the documentation submitted, according to the rate set in the municipal tax bylaws for the current year.
  • By payment card at the General Registry when submitting the documentation.
  • Payment on the day documentation is submitted or the following day at any of the participating banking entities that appear in the self-assessment, or online on the Santa Eulària des Riu Town Hall website..
Regulations
  • Law 7/2013, 26 November, on the legal system for installation, access and exercise of activities in the Balearic Islands (Balearic Islands Official Gazette no. 166, 30 November), the modifications enacted by Law 4/2014, 8 February (Balearic Islands Official Gazette no. 88, 28 June), Law 6/2019, 8 February (Balearic Islands Official Gazette no. 21, 16 February), Decree Law 8/2020, 13 May (Balearic Islands Official Gazette no. 84, 15 May) Law 2/2020, 15 October (Balearic Islands Official Gazette no. 180, 20 October).
  • Santa Eulària des Riu Town Hall tax bylaws.
  • Other bylaws according to activity requested                     
Municipal regulations can be consulted via this website by accessing ‘Town Hall> Bylaws' or ‘Areas/Departments> Urban Planning and Activities'..

Who processes the application?

Urban Planning and Activities Department.

Starting the procedure

At the request of the interested party.

Requirements

Models of standardized forms, well completed and accompanied by the documentation indicated in the same forms.

Processing office

Urban Planning and Activities Department.
C. Mariano Riquer Wallis, 4 (3ª planta)
07840 Santa Eulària des Riu (Ibiza)
Tel. 971332800 (ext. 415)

Adjudicatory body

Local Government Board

Effects of silence Upheld, except in cases where the specific regulations stipulate the contrary in terms of works.
Additional information For additional information, please contact the Urban Planning and Activities Department.